Timescale in Microsoft Project 2013

Hi, when I want to show the week numbers on a construction programme in MSP 2013, the "Week 1" always go back to the start of the earliest activity, however I want to show pre-start activities i.e lead in activities before "Week 1" starts and don't seem to have a solution. I could do this very easily in MSP 2010!!!! Can anyone assist?? Thanks  - Paul

R
Ron Beechey 👤 Member for 23 years 11 months

I handled this issue by setting the project start date to week one of the year in the case of 2015 I selected Jan 4.  That week became week 1 and I was looking for my project to start week 22 so I set the start milestone to this date and the weeks read correctly on a gantt chart print out.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts