Hi
Is it posible in MSP2013 to make a plain old heading?
I just want a title (not header) above sections of some of my tasks, I don't want a date or duration or anything assigned to them, just a plain old title at certain sections.
The only thing I've found of help on the internet is to summarise them in a hammock bar. But that will make my Gantt chart untiday as I dont want hammocks everywhere.
I know it was do-able in Asta Powerproject, is it possible in MSP please?
Ismet
You are a gem, thank you
You can enter a placeholder task (a manually scheduled task with no duration and start/finish dates, instead, just blank). Set task mode to manual and then format the task name as a header.
I'm guessing it's not possible