Headings / Non-Summary tasks without dates / durations etc

C
Christine P 👤 Member for 17 years 3 months

Hi

Is it posible in MSP2013 to make a plain old heading?

I just want a title (not header) above sections of some of my tasks, I don't want a date or duration or anything assigned to them, just a plain old title at certain sections. 

The only thing I've found of help on the internet is to summarise them in a hammock bar.  But that will make my Gantt chart untiday as I dont want hammocks everywhere. 

I know it was do-able in Asta Powerproject, is it possible in MSP please? 

I
Ismet Kocaman 👤 Member for 16 years 4 months

You can enter a placeholder task (a manually scheduled task with no duration and start/finish dates, instead, just blank). Set task mode to manual and then format the task name as a header. 

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts