Is it posible in MSP2013 to make a plain old heading?

I just want a title (not header) above sections of some of my tasks, I don't want a date or duration or anything assigned to them, just a plain old title at certain sections. 

The only thing I've found of help on the internet is to summarise them in a hammock bar.  But that will make my Gantt chart untiday as I dont want hammocks everywhere. 

I know it was do-able in Asta Powerproject, is it possible in MSP please? 

I
Ismet Kocaman 👤 Member for 16 years 3 months

You can enter a placeholder task (a manually scheduled task with no duration and start/finish dates, instead, just blank). Set task mode to manual and then format the task name as a header. 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts