Calendar

Dear Planners,

I created a new calendar different from the standard calendar and I would like this calendar to be assigned to my project, in order to do that, in the project information window I changed the calendar from standard to the calendar I already created.

But, when I added a task calendar column in the gantt chart view, I got "None" under the task calendar, so I have to change it manually.

Best,

Moutaz

M
moutaz aldeib 👤 Member for 22 years 5 months

Thanks Alexandre for this info, it is strange that the project calendar name is not mentioned in the task calendar column.

Best,

Moutaz

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Mountaz,

"None" means that the task is using the project calendar; it is not necessary to assign the project calendar to tasks, except if you want the task calendar to manage a resource loaded task, instead of the resource calendar

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts