% work Complete field

I am updating a project whos resource type is material, when I an updating the % work complete its not not rolling up to show the overal percentage work complete.

I have tried to change the resource type to work, how ever its giving me an overload on the resource before I can specify the maximun number of units and its pushing the project competion out by a couple of years.

How do I show the overall total number of physical work (hrs)

E
Evgeny Z. 👤 Member for 18 years 6 months

Ncube,

1) You need to switch off Automatic Resource Leveling (in MSP 2007 Tools=>Resource Leveling => Manual).

2) MS Project seem to show correctly all work-related values in summary task

See below

 photo Picture_zps894ccbd7.png

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts