% work Complete field

I am updating a project whos resource type is material, when I an updating the % work complete its not not rolling up to show the overal percentage work complete.

I have tried to change the resource type to work, how ever its giving me an overload on the resource before I can specify the maximun number of units and its pushing the project competion out by a couple of years.

How do I show the overall total number of physical work (hrs)

E
Evgeny Z. 👤 Member for 18 years 4 months

Ncube,

1) You need to switch off Automatic Resource Leveling (in MSP 2007 Tools=>Resource Leveling => Manual).

2) MS Project seem to show correctly all work-related values in summary task

See below

 photo Picture_zps894ccbd7.png

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts