Incorrect representation of Progress Line in summary bar??

K
kumar s 👤 Member for 16 years 4 months

Dear All,

 

I have baselined my schedule and started recording the progress.

when i put the progress line,it shows prefectly correct for all the activities.But in the summary bar the Progress line goes ahead of the status date.I have 10 activites under that summary bar and in that 2 activities are over as per the plan.So by logic the progress line should show straight instead of moving ahead.Why is this thing happening...

Please guide me

 

thanks in advance

K
kumar s 👤 Member for 16 years 4 months

Hello All,

 

I have got the reply to my query by Mr Ismet who is a PP Member.

I have been worrying that the Progress line was showing ahead when it should be in a staright line as the actual % is same as Planned %. but MSP draws the Prgress line to the next working activity by default...

I find this thing a bit strange though..

Cheers,

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Kumar,

this is a "normal" behaviour of MS Project; the progress line on summary tasks is supposed to show an average progress status; purely stupid, indeed

Alexandre

I
Ismet Kocaman 👤 Member for 16 years 3 months

Hello Kumar,

If you can send me your schedule at projectuser(at)fastmail.fm, I'll try to help you.

Regards.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts