Dear All,
I have baselined my schedule and started recording the progress.
when i put the progress line,it shows prefectly correct for all the activities.But in the summary bar the Progress line goes ahead of the status date.I have 10 activites under that summary bar and in that 2 activities are over as per the plan.So by logic the progress line should show straight instead of moving ahead.Why is this thing happening...
Please guide me
thanks in advance
Hello All,
I have got the reply to my query by Mr Ismet who is a PP Member.
I have been worrying that the Progress line was showing ahead when it should be in a staright line as the actual % is same as Planned %. but MSP draws the Prgress line to the next working activity by default...
I find this thing a bit strange though..
Cheers,
Kumar,
this is a "normal" behaviour of MS Project; the progress line on summary tasks is supposed to show an average progress status; purely stupid, indeed
Alexandre
Hello Kumar,
If you can send me your schedule at projectuser(at)fastmail.fm, I'll try to help you.
Regards.
Need ur replies guys.......