This can be done in P3 or P6 but I am not familair enough with MSP to know how. In MSP, how do you seperate remaining duration from percent complete?
Thanks,
James Braghini
This can be done in P3 or P6 but I am not familair enough with MSP to know how. In MSP, how do you seperate remaining duration from percent complete?
Thanks,
James Braghini
Hello James,
you can't do that in MSP;
say you have a 6 day task, 50% complete; MSP calculates actual duration = 3 days, remaining duration = 3 days
when you enter a 4 days remaining duration because the task will be longer than expected, %complete becomes 43%
Alexandre