Seperating remaining duartion from % complete

 This can be done in P3 or P6 but I am not familair enough with MSP to know how. In MSP, how do you seperate remaining duration from percent complete?

Thanks,

James Braghini

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Hello James,

you can't do that in MSP;

say you have a 6 day task, 50% complete; MSP calculates actual duration = 3 days, remaining duration = 3 days

when you enter a 4 days remaining duration because the task will be longer than expected, %complete becomes 43%

Alexandre