Moving Tasks from one Summary to another

R
Rajesh K 👤 Member for 14 years 4 months

Hello,

I have a requirement to move some completed tasks from the existing summary task to another new summary task. I am able to do copy-paste. But baseline hours at the new summary task does not show the correct hours. At the new summary task, I would like to get sum of baseline hours for all the individual tasks under it. If I set baseline, it shows incorrect values. Please help me in doing this.

eg: there are 5 tasks under Summary Task - Old and baseline hours is 100. Suppose I have moved 2 tasks having combined baseline hours 30 to "Summary Task - New". As per my requirement, Summary Task - Old should show baseline hours as 70 and Summary Task - New as 30.

 

Thanks and Regards,

Rajesh

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts