Moving Tasks from one Summary to another

R
Rajesh K 👤 Member for 14 years 5 months

Hello,

I have a requirement to move some completed tasks from the existing summary task to another new summary task. I am able to do copy-paste. But baseline hours at the new summary task does not show the correct hours. At the new summary task, I would like to get sum of baseline hours for all the individual tasks under it. If I set baseline, it shows incorrect values. Please help me in doing this.

eg: there are 5 tasks under Summary Task - Old and baseline hours is 100. Suppose I have moved 2 tasks having combined baseline hours 30 to "Summary Task - New". As per my requirement, Summary Task - Old should show baseline hours as 70 and Summary Task - New as 30.

 

Thanks and Regards,

Rajesh

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts