Please advise if it is possible to make the same filtering in MS project as we can do in primavera.. I mean suppose i want all acitvities that start after some date and finish no later that some date....
Thanks much
Please advise if it is possible to make the same filtering in MS project as we can do in primavera.. I mean suppose i want all acitvities that start after some date and finish no later that some date....
Thanks much
Hello,
such filter already exists in MS Project, all versions: go to Project, Filter for, More filters
then select "Should start / finish before"
Alexandre
Note: as I am working with MSP in French, the filter name might be slightly different.