Filters in MS Project

G
G T 👤 Member for 15 years 4 months

Please advise if it is possible to make the same filtering in MS project as we can do in primavera.. I mean suppose i want all acitvities that start after some date and finish no later that some date....

 

Thanks much

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello,

such filter already exists in MS Project, all versions: go to Project, Filter for, More filters

then select "Should start / finish before"

Alexandre

Note: as I am working with MSP in French, the filter name might be slightly different.