I want to assign 6 days calender to the activities & want to calculate the summary task duration based on the 7 days calender,,, is there any way to do this,,,
Thanks & Regards
Mukunda
I want to assign 6 days calender to the activities & want to calculate the summary task duration based on the 7 days calender,,, is there any way to do this,,,
Thanks & Regards
Mukunda
I got it, Thank you Mike,
Hi Mukunda
I don't see why not - just create the two calendars and assign them accoringly.
If MSP won't allow that simple operation then use real software like PowerProject.
Best regards
Mike Testro