Different calender to summary task & Activitis

M
mukunda y 👤 Member for 17 years 6 months

I want to assign 6 days calender to the activities & want to calculate the summary task duration based on the 7 days calender,,, is there any way to do this,,,

 

Thanks & Regards

Mukunda

M
Mike Testro 👤 Member for 20 years 5 months

Hi Mukunda

I don't see why not - just create the two calendars and assign them accoringly.

If MSP won't allow that simple operation then use real software like PowerProject.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts