Different calender to summary task & Activitis

M
mukunda y 👤 Member for 17 years 8 months

I want to assign 6 days calender to the activities & want to calculate the summary task duration based on the 7 days calender,,, is there any way to do this,,,

 

Thanks & Regards

Mukunda

M
Mike Testro 👤 Member for 20 years 7 months

Hi Mukunda

I don't see why not - just create the two calendars and assign them accoringly.

If MSP won't allow that simple operation then use real software like PowerProject.

Best regards

Mike Testro