Dear All,
I have imported a project from P6 to MSP 2007. The import was successful. But I have noticed that the Summary tasks shows the durations in Days while the subtasks / activities are in Hours. Also the predessor linkages are the(activity numbers + period in hours).
How to change the time period from hours to days?
Rohit
Dear Paul H,
Thank you, is there no other solution. I am looking for importing files from P6 to MSP.
Rohit
You have to overtype the durations with the day value.
Ther is an article on my web site under technical articles about importing Microsft Project files into P6 that may inteterest you:
http://www.eh.com.au/technical_papers.html
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.eastwoodharris.com
www.primavera.com.au- a Primavera scheduling software resources site