R
Rohit K 👤 Member for 18 years 2 months

Dear All,

I have imported a project from P6 to MSP 2007. The import was successful. But I have noticed that the Summary tasks shows the durations in Days while the subtasks / activities are in Hours. Also the predessor linkages are the(activity numbers + period in hours).

How to change the time period from hours to days?

Rohit

R
Rohit K 👤 Member for 18 years 2 months

Dear Paul H,

Thank you, is there no other solution. I am looking for importing files from P6 to MSP.

Rohit

P
Paul Harris 👤 Member for 25 years 3 months

You have to overtype the durations with the day value.

Ther is an article on my web site under technical articles about importing Microsft Project files into P6 that may inteterest you:

http://www.eh.com.au/technical_papers.html

Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

www.eastwoodharris.com

www.primavera.com.au- a Primavera scheduling software resources site

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts