HOW TO - Throw the progress in MS Project

Member for

17 years 5 months

Thanx Alexandre

Member for

14 years 7 months

hi....one small question..Is it able to assign different calenders in a same project for different activities....if so how? Will it affect the total duration for the entire project?

Member for

19 years 11 months

Go to Google Groups. Find the group microsoft.public.project. Search the group for my name or for key words such as "progress" etc and there find many posts and discussions concerning this topic and with explicit instructions.

Member for

14 years 8 months

after that you can try, tools,tracking, update project, & re-schedule. From there you would be able to know how further delay of your project will be with the current project progress % that you have at the moment.

D

Member for

22 years 9 months

Jhorbam,

if I understand you well, you want to update your project and see which activities are delayed and which would finish later than planned

first of all, you should save a baseline for the project and display it: Tools, Tracking, Save baseline; then View, Tracking Gantt and View, Tables, Tracking

Tracking Gantt will display the baseline bars together with the current bars, and Tracking Table will display all the necessary fields for you to enter the actual dates and duration of the tasks

if some tasks must be completed before a specific date, enter a Not Later Than constraint on these tasks before you update the project for the first time

Hope this helps

Alexandre