No problem, Dan -it’s what we’re here for!

Member for

15 years 9 months

Hi Gary,



Thanks for your respones!



/ Dan


Member for

16 years 7 months

1) Right click on the bar chart, go to "Bar Styles"

2) Insert a new row BELOW the existing milestone row

3) select appearance, including colour

4) In ’Show for’ Column, enter "Milestone,Critical"

5) Enter either Start or Finish in BOTH ’From’ and ’To’ fields