Critical milestone

G
Gary Whitehead 👤 Member for 17 years 4 months

1) Right click on the bar chart, go to "Bar Styles"

2) Insert a new row BELOW the existing milestone row

3) select appearance, including colour

4) In ’Show for’ Column, enter "Milestone,Critical"

5) Enter either Start or Finish in BOTH ’From’ and ’To’ fields





Cheers,



G