You can create an additional custom Bar Style on top of your Summary Bar Style and use available/spare date field for the purpose of fixing a start and finish date of your line.



Summary Line

R
Rodel Marasigan 👤 Member for 19 years 7 months

Russ,

Try Gridlines-> Gantt rows. You can change the interval but not selecting only summary. You can collapse to summary level if required.