Swim Lanes MS Project 2003
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
You can create an additional custom Bar Style on top of your Summary Bar Style and use available/spare date field for the purpose of fixing a start and finish date of your line.

Russ,
Try Gridlines-> Gantt rows. You can change the interval but not selecting only summary. You can collapse to summary level if required.