Hi All
Even within the limited scope of MSP surely the task calendar will conflict with the resource calendar.
Which is the overide?
Is there not an option to toggle "resource calendar as task"?
If not why not.
Best regards
Mike Testro.
It works, Thanks!
//Dan
Dan,
If you just want to make a "curtain" in your Gantt chart to show the possibility of vacation, then just make a calendar called e.g. "Possible Periods with Vacation" with the respective days marked as non-working time.
Let all resources keep their present assigned calendars, but under "Format-Timescale-Nonworking Time (tab)" choose "Possible Periods with Vacation" in the Calendar-field. That will only have an influence on what is shown on the Gantt chart and not on any resources.
Regards,
Bo
Thank you Rodel!
I wasn’t think that far :-)
Regards
Dan
Dan,
Create a calendar that reflects all those vacation dates and assigned only to those resource that having vacation as base calendar.