Mark in the bar view

M
Mike Testro 👤 Member for 20 years 7 months

Hi All



Even within the limited scope of MSP surely the task calendar will conflict with the resource calendar.



Which is the overide?



Is there not an option to toggle "resource calendar as task"?



If not why not.



Best regards



Mike Testro.

B
Bo Johnsen 👤 Member for 20 years 5 months

Dan,



If you just want to make a "curtain" in your Gantt chart to show the possibility of vacation, then just make a calendar called e.g. "Possible Periods with Vacation" with the respective days marked as non-working time.



Let all resources keep their present assigned calendars, but under "Format-Timescale-Nonworking Time (tab)" choose "Possible Periods with Vacation" in the Calendar-field. That will only have an influence on what is shown on the Gantt chart and not on any resources.



Regards,



Bo

R
Rodel Marasigan 👤 Member for 19 years 9 months

Dan,

Create a calendar that reflects all those vacation dates and assigned only to those resource that having vacation as base calendar.

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts