Project Overview

L
Lo Gary 👤 Member for 16 years 5 months
M
mukunda y 👤 Member for 17 years 8 months

MSP variance is ok.



we can use formula to calculate variance to our requirements(whatever may be the baseline).

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Gary & Samer,

it is not possible in MS Project to select a specific baseline as the "default baseline" against which MSP would compare "Actual" to calculate a Variance.

Project overview’s Variance is always calculated between Actual Start / Finish and Baseline Start / Finish; where "Baseline" stands for "Initial Baseline" with no number (i.e. <> "Baseline1", ...

if you want to save a 2nd baseline and have it used in the Variance, you will have to save "Baseline" as "Baseline1" first, then save the current project as "Initial Baseline (no number)" again

Alexandre

S
Samer Zawaydeh 👤 Member for 17 years 11 months

Dear Gary,



The variance is between any two schedules that you select.



With kind regards,



Samer

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts