Multiple critical paths
Forum Sponsor
Top Posters
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Lo Gary,
It will be depends how the job are being manage. In your case I believed multiple projects would be better so it become more independent and allocated to each responsible supervisor or manager. It’s like Projects on an Enterprise level. Having critical path for each would be a good guide for each sections so they can manage it separately. It is up to you how you’re going to handle that situation in one Project.
Dear,
How about if my project is divided into different phases with different completion dates. Is it recommended to use multiple projects would be better, so that each phase has its own critical path ?
"TOOLS-OPTIONS, clicking CALCULATE MULTIPLE CRITICAL PATHS at the CALCULATION tab would give the same result??"
yes i think based on individual finish date
Dear Gary,
Usually the Contractor is ask to prepare the Schedule or Program of Works for the scope that they are going to deliver. In this case, they will submit one Schedule.
If you are working on the Client side and you have 1+ contractors, then it is your responsibility to manage them in most cases. If you are in this category, then you need to use multiple projects.
With kind regards,
Samer