Multiple critical paths

Member for

19 years

Lo Gary,

It will be depends how the job are being manage. In your case I believed multiple projects would be better so it become more independent and allocated to each responsible supervisor or manager. It’s like Projects on an Enterprise level. Having critical path for each would be a good guide for each sections so they can manage it separately. It is up to you how you’re going to handle that situation in one Project.

Member for

15 years 9 months

Dear,



How about if my project is divided into different phases with different completion dates. Is it recommended to use multiple projects would be better, so that each phase has its own critical path ?

Member for

18 years 3 months

"TOOLS-OPTIONS, clicking CALCULATE MULTIPLE CRITICAL PATHS at the CALCULATION tab would give the same result??"



yes i think based on individual finish date

Member for

17 years 3 months

Dear Gary,



Usually the Contractor is ask to prepare the Schedule or Program of Works for the scope that they are going to deliver. In this case, they will submit one Schedule.



If you are working on the Client side and you have 1+ contractors, then it is your responsibility to manage them in most cases. If you are in this category, then you need to use multiple projects.



With kind regards,



Samer