Microsoft Project Member for 15 years 9 months Member for 15 years 9 months Submitted by Dan Mårtensson on Wed, 2010-03-24 06:06 Permalink RE: planed hours Thank you, this works fine! //Dan Member for 19 years 11 months Member for 19 years 11 months Submitted by Trevor Rabey on Tue, 2010-03-23 12:44 Permalink RE: planed hours Yes. Must have in mind "Planned as of when?". Say it is as planned as of the day before the project started. Get the version of the plan that you had on that day. Set the status date to today. Use the Tracking Gantt and Tracking Table. Also, have available the Tracking Toolbar. Also, format the gridlines to show the status date as a vertical red line on the chart Select all tasks. Click the Update as scheduled button om the Tracking Toolbar (2nd from left). Then see the Actual Work column in the Tracking Table or the Work Table. Log in or register to post comments
Member for 15 years 9 months Member for 15 years 9 months Submitted by Dan Mårtensson on Wed, 2010-03-24 06:06 Permalink RE: planed hours Thank you, this works fine! //Dan
Member for 19 years 11 months Member for 19 years 11 months Submitted by Trevor Rabey on Tue, 2010-03-23 12:44 Permalink RE: planed hours Yes. Must have in mind "Planned as of when?". Say it is as planned as of the day before the project started. Get the version of the plan that you had on that day. Set the status date to today. Use the Tracking Gantt and Tracking Table. Also, have available the Tracking Toolbar. Also, format the gridlines to show the status date as a vertical red line on the chart Select all tasks. Click the Update as scheduled button om the Tracking Toolbar (2nd from left). Then see the Actual Work column in the Tracking Table or the Work Table.
Member for
15 years 9 monthsRE: planed hours
Thank you, this works fine!
//Dan
Member for
19 years 11 monthsRE: planed hours
Yes.
Must have in mind "Planned as of when?".
Say it is as planned as of the day before the project started.
Get the version of the plan that you had on that day.
Set the status date to today.
Use the Tracking Gantt and Tracking Table.
Also, have available the Tracking Toolbar.
Also, format the gridlines to show the status date as a vertical red line on the chart
Select all tasks.
Click the Update as scheduled button om the Tracking Toolbar (2nd from left).
Then see the Actual Work column in the Tracking Table or the Work Table.