planed hours
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Thank you, this works fine!
//Dan
Yes.
Must have in mind "Planned as of when?".
Say it is as planned as of the day before the project started.
Get the version of the plan that you had on that day.
Set the status date to today.
Use the Tracking Gantt and Tracking Table.
Also, have available the Tracking Toolbar.
Also, format the gridlines to show the status date as a vertical red line on the chart
Select all tasks.
Click the Update as scheduled button om the Tracking Toolbar (2nd from left).
Then see the Actual Work column in the Tracking Table or the Work Table.