planed hours

T
Trevor Rabey 👤 Member for 20 years 7 months

Yes.

Must have in mind "Planned as of when?".

Say it is as planned as of the day before the project started.

Get the version of the plan that you had on that day.

Set the status date to today.

Use the Tracking Gantt and Tracking Table.

Also, have available the Tracking Toolbar.

Also, format the gridlines to show the status date as a vertical red line on the chart

Select all tasks.

Click the Update as scheduled button om the Tracking Toolbar (2nd from left).

Then see the Actual Work column in the Tracking Table or the Work Table.