Hi Assaf,



It can be done in MS Project but it’s time consuming and requires a lot of manual intervention each time you update the task.



View > More Views > Task Usage



Change the timescales so that the lower tier display weeks or days and adjust the work assignment so that the first week has a total of 1d effort, the second week has a total of 4d effort and the third week has a 5d total of effort.



I wouldn’t recommend you do this though, you’ll probably end up amending the resources 24hrs a day rather than managing and updating the schedule.



Regards,



Darren

R
Raphael M. Dua 👤 Member for 25 years 6 months

assaf f



If you need to do this across your whole project, then MS Project will not do it.

Try Micro Planner X-Pert for Windows as it allows up to 20 separate entries for a resource per task



Raf

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts