% Allocation

A
assaf f 👤 Member for 18 years 5 months
D
Darren Kosa 👤 Member for 18 years 3 months

Hi Assaf,



It can be done in MS Project but it’s time consuming and requires a lot of manual intervention each time you update the task.



View > More Views > Task Usage



Change the timescales so that the lower tier display weeks or days and adjust the work assignment so that the first week has a total of 1d effort, the second week has a total of 4d effort and the third week has a 5d total of effort.



I wouldn’t recommend you do this though, you’ll probably end up amending the resources 24hrs a day rather than managing and updating the schedule.



Regards,



Darren

R
Raphael M. Dua 👤 Member for 25 years 4 months

assaf f



If you need to do this across your whole project, then MS Project will not do it.

Try Micro Planner X-Pert for Windows as it allows up to 20 separate entries for a resource per task



Raf

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts