% Allocation

Member for

17 years 9 months

Hi Assaf,



It can be done in MS Project but it’s time consuming and requires a lot of manual intervention each time you update the task.



View > More Views > Task Usage



Change the timescales so that the lower tier display weeks or days and adjust the work assignment so that the first week has a total of 1d effort, the second week has a total of 4d effort and the third week has a 5d total of effort.



I wouldn’t recommend you do this though, you’ll probably end up amending the resources 24hrs a day rather than managing and updating the schedule.



Regards,



Darren

Member for

24 years 9 months

assaf f



If you need to do this across your whole project, then MS Project will not do it.

Try Micro Planner X-Pert for Windows as it allows up to 20 separate entries for a resource per task



Raf