MSP: Remaining work - Time Phased
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Thanks Alex, I will give that a try.
Kayode,
you cannot export any other data that are not included in the list "Export Timescaled Data in Excel"
another way is to show the Using Tasks view, display the fields you want in the distribution (rightmost) pane, and select the necessary data to paste in Excel
Alexandre
What data do you want?
Hi Lewis.
Apologies for confusion, It should read: Export time phased data from MS Project to MS Excel.
I have used the analyze timescaled data tab, but the data I want is not included in available list.
Import or export?
You can export timescaledata from Project (and load it into Excel). Or, from a different vantage point, you can import into Excel data exported from Project.
You cannot export timescaledata from Excel (and load it into Project). Or, from a different vantage point, you cannot import into Project data exported from Excel. (Well, you can but its not easy.)
Display the Analysis toolbar
Click on "Analyze TimeScaled Data in Excel"
Answer the various prompts.