MSP: Remaining work - Time Phased

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Kayode,

you cannot export any other data that are not included in the list "Export Timescaled Data in Excel"

another way is to show the Using Tasks view, display the fields you want in the distribution (rightmost) pane, and select the necessary data to paste in Excel

Alexandre

K
Kayode Oni 👤 Member for 19 years

Hi Lewis.

Apologies for confusion, It should read: Export time phased data from MS Project to MS Excel.

I have used the analyze timescaled data tab, but the data I want is not included in available list.

L
L.E.N. Lewis 👤 Member for 18 years 10 months

Import or export?



You can export timescaledata from Project (and load it into Excel). Or, from a different vantage point, you can import into Excel data exported from Project.



You cannot export timescaledata from Excel (and load it into Project). Or, from a different vantage point, you cannot import into Project data exported from Excel. (Well, you can but it’s not easy.)



Display the Analysis toolbar

Click on "Analyze TimeScaled Data in Excel"

Answer the various prompts.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts