Home Cinema

H
Hemanth Kumar 👤 Member for 23 years 8 months

Thank You



I Discussed With My Supplier and Formulated The Plan

Thank You For Your Interest & Helpful Mind

S
Samer Zawaydeh 👤 Member for 17 years 11 months

Dear Hemanth,



I have checked with our local Low Current Supplier, and they informed me that it is totally dependent on the system that you are installing.



So I suggest that you discuss the issue with the supplier and formulate a completion plan as per his sequence of work.



Best Regards,



Samer

H
Hemanth Kumar 👤 Member for 23 years 8 months

Thank you sameer

but i was looking for the finer details

install projector,lay HDMI cable , install speakers etc

S
Samer Zawaydeh 👤 Member for 17 years 11 months

Dear Hemanth,



Kindly consider the following:



1) Material submital approval

2) Shop drawings approval

3) Procurement

4) Construction

a. 1st fix: After block work and before plastering

b. 2nd fix: before complete plastering

c. 3rd fix: before complete painting

5) Commissioning: few days before handing over.

6) Programming: after moving in



If you need more specific detail, the best source would be the specialist who is going to install the system for you.



Best Regards,



Samer

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts