Just to reply for fun.
MSP is not allowed to define activities type like P3/P6, the activities will automatically change to milestone when you assign the duration to 0.
But MSP (compare w/ P3) is allow to create hyperlink within cell value, make use for it, you will found more fun!!! ;)