activity type

J
Jon Ward 👤 Member for 18 years 1 month
C
Chee Sean Moo 👤 Member for 19 years 7 months

Just to reply for fun.



MSP is not allowed to define activities type like P3/P6, the activities will automatically change to milestone when you assign the duration to 0.



But MSP (compare w/ P3) is allow to create hyperlink within cell value, make use for it, you will found more fun!!! ;)