Creating Targets in Project

J
Jon Ward 👤 Member for 17 years 11 months
J
Jon Ward 👤 Member for 17 years 11 months

thanks Darren,

very very much appreciated

best regards

jon

D
Darren Kosa 👤 Member for 18 years 3 months

Jon,



OK, I’m with you now. Setting the baseline is straightforward enough Tools > Tracking > Save Baseline. Check the ‘Save Baseline’ and ‘Entire Project’ radio buttons and click OK.



Displaying Planned % Complete is a little more difficult and requires some customisation.



Check out the thread below that Niek Zonneveld started, it should give you the solution you need.



Display Baseline Percent Complete In MS Project



Regards,



Darren

J
Jon Ward 👤 Member for 17 years 11 months

the dark side lol,,

in P3 you can basically create an entire copy of your project i.e baseline the schedule the display the activity bars for every activity below the ’live’ activity bars,, that way you can see easily what has slipped and what is ahead of schedule,, you can also show Planned Percentage (of the baseline) against the actual percentage

many thanks

D
Darren Kosa 👤 Member for 18 years 3 months

Hi Jon,



Welcome to the dark side. :o)



I use MS Project but haven’t used Primavera, so if you could expand a little on what you mean by targets, then I may (or may not) be able to help.



Regards,



Darren

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts