OK, I’m with you now. Setting the baseline is straightforward enough Tools > Tracking > Save Baseline. Check the ‘Save Baseline’ and ‘Entire Project’ radio buttons and click OK.
Displaying Planned % Complete is a little more difficult and requires some customisation.
Check out the thread below that Niek Zonneveld started, it should give you the solution you need.
in P3 you can basically create an entire copy of your project i.e baseline the schedule the display the activity bars for every activity below the live activity bars,, that way you can see easily what has slipped and what is ahead of schedule,, you can also show Planned Percentage (of the baseline) against the actual percentage
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
thanks Darren,
very very much appreciated
best regards
jon
Jon,
OK, I’m with you now. Setting the baseline is straightforward enough Tools > Tracking > Save Baseline. Check the ‘Save Baseline’ and ‘Entire Project’ radio buttons and click OK.
Displaying Planned % Complete is a little more difficult and requires some customisation.
Check out the thread below that Niek Zonneveld started, it should give you the solution you need.
Display Baseline Percent Complete In MS Project
Regards,
Darren
the dark side lol,,
in P3 you can basically create an entire copy of your project i.e baseline the schedule the display the activity bars for every activity below the live activity bars,, that way you can see easily what has slipped and what is ahead of schedule,, you can also show Planned Percentage (of the baseline) against the actual percentage
many thanks
Hi Jon,
Welcome to the dark side. :o)
I use MS Project but havent used Primavera, so if you could expand a little on what you mean by targets, then I may (or may not) be able to help.
Regards,
Darren