Critical Path / Critical Activities

A
Alex Logie 👤 Member for 18 years 4 months
A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Alex,

Project, Filter for, Critical Task

1.Is the last task in your schedule a milestone? then MS Project does not display critical milestones in red and not-critical ones in blue as it does for norlmal tasks

Is the last task milestone a critical one?

2. Do you have recurring tasks in your schedule?

then check the Start No Earlier Than date of the last occurence, and the one before last, ... until you find that this occurence is starting later than the last task at the bottom of the schedule

Hope this help

Alexandre

T
Trevor Rabey 👤 Member for 20 years 6 months

Check the Schedule Table to see the ES, EF, LS, LF, free slack and total slack.



Run the Gantt Chart Wizard to format Critical Tasks red.



Check Tools, Options, calculation to see that Critical is defined as zero total slack.

L
L.E.N. Lewis 👤 Member for 18 years 10 months

Tools | Options | Calculation-tab.

Put a check mark in the box "Calculate multiple critical paths"



View | Tracking Gantt



(I *so* miss NZ -- did the Milford, went as far north as 90 Mile Beach, would love to live in Napier.)

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts