MS Project 2000 Finish Start Link
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Thanks, but all of my start and end times are identical in the project, task, and resource calendars.
Hi Ben,
Have you been to the calendar options in the option menu? Here you can change the default settings of your calendar such as default starting time, default finish time etc..
Just go to TOOLS, OPTIONS, CALENDAR...
Maybe this helps..
Best regards,
Gerry
Thats what I am trying to do, but MS Project will not change the start or finish time in some instances. Its a predessesor problem, but the predessesor finishes ends at the end of the day and shift, so there appears to be no issue.
Thank you for the help. Anyone else know whats wrong?
Hi Benjamin,
Unfortumately, I did it task by task also when this happened to me. You may change the date format to hours to lessen the difficulty of doing it.
Good luck.
Se
Yeah something is going on with the constraint date where some tasks are starting at 5:00 pm when they should start at 8:00 AM and Finish at 8:00 PM or 8:00 AM when they should Finis at 5:00 PM.
I have a lot of Tasks how do I change this without going task by task? I already tried Find and Replace.
I too hate what you hate. What can we do?
Try checking the timescale in hours or change the date format with hours. Its possible that the predecessor is finishing at 4PM while the successor is starting at 4:01PM of the same day.
Funny isnt it? What do you expect from Mickey Mouse?
Good luck
Se
P.S. If this is the case, please dont ask me why this is so, ask mickey mouse.