Have you been to the calendar options in the option menu? Here you can change the default settings of your calendar such as default starting time, default finish time etc..
Thats what I am trying to do, but MS Project will not change the start or finish time in some instances. Its a predessesor problem, but the predessesor finishes ends at the end of the day and shift, so there appears to be no issue.
Thank you for the help. Anyone else know whats wrong?
Yeah something is going on with the constraint date where some tasks are starting at 5:00 pm when they should start at 8:00 AM and Finish at 8:00 PM or 8:00 AM when they should Finis at 5:00 PM.
I have a lot of Tasks how do I change this without going task by task? I already tried Find and Replace.
Try checking the timescale in hours or change the date format with hours. Its possible that the predecessor is finishing at 4PM while the successor is starting at 4:01PM of the same day.
Funny isnt it? What do you expect from Mickey Mouse?
Good luck
Se
P.S. If this is the case, please dont ask me why this is so, ask mickey mouse.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks, but all of my start and end times are identical in the project, task, and resource calendars.
Hi Ben,
Have you been to the calendar options in the option menu? Here you can change the default settings of your calendar such as default starting time, default finish time etc..
Just go to TOOLS, OPTIONS, CALENDAR...
Maybe this helps..
Best regards,
Gerry
Thats what I am trying to do, but MS Project will not change the start or finish time in some instances. Its a predessesor problem, but the predessesor finishes ends at the end of the day and shift, so there appears to be no issue.
Thank you for the help. Anyone else know whats wrong?
Hi Benjamin,
Unfortumately, I did it task by task also when this happened to me. You may change the date format to hours to lessen the difficulty of doing it.
Good luck.
Se
Yeah something is going on with the constraint date where some tasks are starting at 5:00 pm when they should start at 8:00 AM and Finish at 8:00 PM or 8:00 AM when they should Finis at 5:00 PM.
I have a lot of Tasks how do I change this without going task by task? I already tried Find and Replace.
I too hate what you hate. What can we do?
Try checking the timescale in hours or change the date format with hours. Its possible that the predecessor is finishing at 4PM while the successor is starting at 4:01PM of the same day.
Funny isnt it? What do you expect from Mickey Mouse?
Good luck
Se
P.S. If this is the case, please dont ask me why this is so, ask mickey mouse.