MSP Baslines
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Andrew
Make sure the activities are logic linked correctly, that you have no constraints, you have a critical path identified wthin the project etc.
When updating a project you must save the baseline firstly ( Save Baseline ).
Go into Tracking Gantt.
Insert Columns .... Activity Name / Baseline start / baseline finish / Actual Start / Actual Finish Per complete
Go to Tools > Tracking > Progress Lines > Input the data / progress line date.
Input the ACTUAL Start and Finish Dates against each activity. If some activities have started but are incomplete then you must put in a percentage.
The project is now being progressed.
Hello Alexandre ,
Yes I am posting the progress in the tracking option.
Andrew
Andrew,
are you entering the progress in the tracking table fields?
Alexandre