Make sure the activities are logic linked correctly, that you have no constraints, you have a critical path identified wthin the project etc.
When updating a project you must save the baseline firstly ( Save Baseline ).
Go into Tracking Gantt.
Insert Columns .... Activity Name / Baseline start / baseline finish / Actual Start / Actual Finish Per complete
Go to Tools > Tracking > Progress Lines > Input the data / progress line date.
Input the ACTUAL Start and Finish Dates against each activity. If some activities have started but are incomplete then you must put in a percentage.
The project is now being progressed.
Hello Alexandre ,
Yes I am posting the progress in the tracking option.
Andrew
Andrew,
are you entering the progress in the tracking table fields?
Alexandre