MS Project Server - New Forecast Dates
Forum Sponsor
Top Posters
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
Scott,
the administrator can allow the resources to enter actual hours per day / actual days per week instead of % complete; I cannot explain the whole process as I do not have MS Project Server currently loaded on my traveling PC
this way, the resource would enter actual hours the day the task actually starts, and not the day the task should start
Does it help?
Alexandre