MS Project Server - New Forecast Dates

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

Scott,

the administrator can allow the resources to enter actual hours per day / actual days per week instead of % complete; I cannot explain the whole process as I do not have MS Project Server currently loaded on my traveling PC

this way, the resource would enter actual hours the day the task actually starts, and not the day the task should start

Does it help?

Alexandre