Ms Project and Baselines
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
hI SHEILA,
Do not worry that much about it, just give them a swift kick under the rectum, and they will reply.
Regards,
Philip
Sheila,
a star, really? eh, eh, eh...
a star ... I am a star ...
Alexandre
Alexandre - you are an absolute star! Thank you very much!
Sheila
Sheila,
1. Go to Format, Bar Styles; then add a bar that represents "Normal" tasks, begins with "Baseline 1 Start" and ends with "Baseline 1 Finish"; do the same for any other baseline you want to display on screen
2. To save "Baseline x" as "Baseline y", go to Tools, Tracking, Save (original) baseline, then select Save interim plan and copy "Baseline x" to "Baseline y".
Hope it helps,
Alexandre
Hi Sheila,
The questions is simple, however as I am not a full time MSP user the answers are noet coming of the tp of my head, but there is always work arounds to keep this type of information. make sure you save every file/version with its baseline when it is set, and under a different name. at least this keeps the history, as MSP does not have unique IDs at least you can go back and find the info at a later stage, itis cumbersom, but at least you are not losing info.
Regards
Philip