1. Go to Format, Bar Styles; then add a bar that represents "Normal" tasks, begins with "Baseline 1 Start" and ends with "Baseline 1 Finish"; do the same for any other baseline you want to display on screen
2. To save "Baseline x" as "Baseline y", go to Tools, Tracking, Save (original) baseline, then select Save interim plan and copy "Baseline x" to "Baseline y".
The questions is simple, however as I am not a full time MSP user the answers are noet coming of the tp of my head, but there is always work arounds to keep this type of information. make sure you save every file/version with its baseline when it is set, and under a different name. at least this keeps the history, as MSP does not have unique IDs at least you can go back and find the info at a later stage, itis cumbersom, but at least you are not losing info.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
hI SHEILA,
Do not worry that much about it, just give them a swift kick under the rectum, and they will reply.
Regards,
Philip
Sheila,
a star, really? eh, eh, eh...
a star ... I am a star ...
Alexandre
Alexandre - you are an absolute star! Thank you very much!
Sheila
Sheila,
1. Go to Format, Bar Styles; then add a bar that represents "Normal" tasks, begins with "Baseline 1 Start" and ends with "Baseline 1 Finish"; do the same for any other baseline you want to display on screen
2. To save "Baseline x" as "Baseline y", go to Tools, Tracking, Save (original) baseline, then select Save interim plan and copy "Baseline x" to "Baseline y".
Hope it helps,
Alexandre
Hi Sheila,
The questions is simple, however as I am not a full time MSP user the answers are noet coming of the tp of my head, but there is always work arounds to keep this type of information. make sure you save every file/version with its baseline when it is set, and under a different name. at least this keeps the history, as MSP does not have unique IDs at least you can go back and find the info at a later stage, itis cumbersom, but at least you are not losing info.
Regards
Philip