OK, this just means that you can’t paste a link just anywhere you like, just as you can’t type data into just any cell. I suspect that you are trying to paste dates into a Summary Task (heading) or similar. These are always calculated by MSP from the dates of the sub-tasks. Try pasting your link into a task cell.

Member for

20 years 6 months

After following the instructions a box appears stating: The paste link failed. You Cannot paste into a field that Project calculates automatically?



Please advise

Thanks

Lee

Member for

22 years 9 months

Lee,

1. in Excel, select the appropriate cells and click Edit, Copy

2. in MS Project, select the appropriate cells and click Edit, Paste special, with link, text

3. DO NOT move the files, or you will have to refresh the link

Cheers,

Alexandre