Tasks showing up as critical that are not

T
tim Rodriguez 👤 Member for 20 years 1 month

Alexandre,

Thanks for your reply. In the interim time period between my original post and now.....I realized that when we converted the file from P3, some resource calendars came over as well. These calendars were driving activities critcal. So thanks again for the reply!

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello,

it is a difficult question to answer without having the file on screen.

do you have resources being assigned on tasks and presumably THIS task? what about calendars?

where is the task situated in the project duration?

If you want to send me your files, just give me a Personal Message.

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts