Tasks showing up as critical that are not

T
tim Rodriguez 👤 Member for 20 years 3 months

Alexandre,

Thanks for your reply. In the interim time period between my original post and now.....I realized that when we converted the file from P3, some resource calendars came over as well. These calendars were driving activities critcal. So thanks again for the reply!

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Hello,

it is a difficult question to answer without having the file on screen.

do you have resources being assigned on tasks and presumably THIS task? what about calendars?

where is the task situated in the project duration?

If you want to send me your files, just give me a Personal Message.

Alexandre

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts