Tasks showing up as critical that are not
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Alexandre,
Thanks for your reply. In the interim time period between my original post and now.....I realized that when we converted the file from P3, some resource calendars came over as well. These calendars were driving activities critcal. So thanks again for the reply!
Hello,
it is a difficult question to answer without having the file on screen.
do you have resources being assigned on tasks and presumably THIS task? what about calendars?
where is the task situated in the project duration?
If you want to send me your files, just give me a Personal Message.
Alexandre