Tasks showing up as critical that are not
Forum Sponsor
Top Posters
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Alexandre,
Thanks for your reply. In the interim time period between my original post and now.....I realized that when we converted the file from P3, some resource calendars came over as well. These calendars were driving activities critcal. So thanks again for the reply!
Hello,
it is a difficult question to answer without having the file on screen.
do you have resources being assigned on tasks and presumably THIS task? what about calendars?
where is the task situated in the project duration?
If you want to send me your files, just give me a Personal Message.
Alexandre